In Mertens v. Home Freeholds Company (1921),2 K.B. 526, where the Court approved the law on this point as stated in an earlier edition of Hudson. In that case the contractor had undertaken to build to the roofing and the Court held:- The proper measure of damages was what it cost the plaintiff to complete the house substantially as it was originally intended and in a reasonable manner at the earliest moment he was allowed to proceed with the work, less any amount which would have been due and payable by the defendant to the plaintiff, had the defendant completed the house to the roofing at the time agreed by the terms of the contract.
DAMAGES FOR BREACH OF CONTRACT IS BASED ON RESTITUTIO IN INTEGRUM
In awarding damages in an action founded on breach of contract, the rule to be applied is restitutio in integrum that is, in so far as the damages are not too remote, the plaintiff shall be restored as far as money can do it, to the position in which he would have been if the...