Judiciary-Poetry-Logo
JPoetry

SUBJECT MATTER OF ARBITRATION MUST BE WITHIN THE ORIGINAL CONTRACT

Dictum

In BAKER MARINE (NIG) v. CHEVRON NIG. LTD (2006) 6 SC 21 at Pg. 31 &37; (2006) FWLR Pt. 326 Pg. 235 at 250, the issue in this Court was whether damages for the tort of conspiracy as opposed to that of breach of contract can be at large and that aggravated damages could be claimed and sustained by the arbitral award. This Court held that any award would be outside the arbitration agreement and the arbitrators are not allowed to re-write the arbitration agreement to include extraneous issues or parties outside the substantive contract between the parties.

Was this dictum helpful?

SHARE ON

AN ARBITRATION AGREEMENT IS A SEPARATE CONTRACT

The Courts have always upheld the autonomy and independence of the arbitration clause in the contract. The arbitration agreement may be drawn up separately or may form part of the transaction between the parties. Where the arbitration clause is part of the contract, it is nevertheless regarded in law as a separate contract. In HEYMAN v. DARWIN LTD (1942) A.C 356 at pp. 373-4, the Court in the United Kingdom in considering the legal status of such a clause in a contract, observed: ” … an arbitration clause in a contract is quite distinct from the other clauses. The other clauses set out the obligations which the parties undertake towards each other, but the arbitration clause does not impose on one of the parties an obligation in favour of the other. It embodies the agreement of both parties that, if any dispute arises with regard to the obligations which the one party has undertaken to the other such dispute shall be settled by a Tribunal of their own Constitution.”

— H.M. Ogunwumiju, JSC. UBA v Triedent Consulting Ltd. (SC.CV/405/2013, July 07, 2023)

Was this dictum helpful?

PARTIES ARE BOUND BY ARBITRAL AWARD

Once parties have consented to arbitration, they have also consented to accept the final award by the arbitrator.

– Nimpar, JCA. Dunlop v. Gaslink (2018)

Was this dictum helpful?

ARBITRAL AWARD IS BINDING ON PARTIES

It is important to note here that all these facts were before Longe J when the application which led to this appeal was being considered. It is also equally important to say that it was open to either of the parties to apply to the Court in England to set aside, the award if either felt that the arbitrator had misconducted himself or that the award on its face was wrong. The necessary consequence of the award is that if neither of the parties applied to set it aside, it was liable to be enforced as binding on the parties.

— Oguntade, JCA. Adwork Ltd. v Nigeria Airways Ltd. (1999) – CA/L/156/99

Was this dictum helpful?

P&ID DID NOT ENTER THE CONTRACT TO JUST GET A SETTLEMENT VIA ARBITRATION, WITH THE INTENTION OF NOT PERFORMING

490. Here, I am satisfied P&ID did intend to perform the GSPA when it entered into it, and that there were means by which it could have done so. Nigeria has characterised the GSPA as a sham and contended that P&ID as a BVI-registered company with no obvious assets, no relevant experience and few employees, had no genuine intention of performing the GSPA, and would never have been able to do so. However P&ID did not have to contemplate performing the GSPA itself with its assets, experience and employees. This is not, as it represented, because it could simply use the work on Project Alpha to perform the GSPA. It is rather because ICIL Group had shown in the past that they could contract in. 491. Whilst P&ID was prepared to bribe in the course of its business, I do not accept it was of the sophistication to conceive at the contract stage a plan to extract large sums of money from Nigeria by means of an arbitration or a corrupt settlement. Consistently, P&ID did not use the GSPA to move directly to arbitration at the first available opportunity. I have found it did not (as alleged by Nigeria) corrupt Mr Shasore SAN. And it appointed, in Sir Anthony Evans, an arbitrator of unquestioned experience, expertise and independence. 492. It is in these circumstances that I have reached the conclusion that the present is not a case in which, when the parties entered into the GSPA, P&ID’s intention was not to perform it but simply to use it as a device to get an award or settlement. However that is not the end of Nigeria’s section 68(2)(g) challenge.

— R. Knowles CBE. FRN v. Process & Industrial Developments Limited [2023] EWHC 2638 (Comm)

Was this dictum helpful?

IMPORTANCE OF PUTTING GOOD REPRESENTATION IN ARBITRAL PROCEEDINGS BY PARTIES

587. Notwithstanding Nigeria’s allegations, I have not found Nigeria’s lawyers in the Arbitration to be corrupt. But the case has shown examples where legal representatives did not do their work to the standard needed, where experts failed to do their work, and where politicians and civil servants failed to ensure that Nigeria as a state participated properly in the Arbitration. The result was that the Tribunal did not have the assistance that it was entitled to expect, and which makes the arbitration process work. And Nigeria did not in the event properly consider, select and attempt admittedly difficult legal and factual arguments that the circumstances likely required. Even without the dishonest behaviour of P&ID, Nigeria was compromised. 588. But what is an arbitral tribunal to do? The Tribunal in the present case allowed time where it felt it could and applied pressure where it felt it should. Perhaps some encouragement to better engagement can be seen as well. Yet there was not a fair fight. And the Tribunal took a very traditional approach. But was the Tribunal stuck with what parties did or did not appear to bring forward? Could and should the Tribunal have been more direct and interventionist when it was so clear throughout the Arbitration that Nigeria’s lawyers were not getting instructions, or when at the quantum hearing Nigeria’s then Leading Counsel, Chief Ayorinde, was failing to put necessary points to experts to test their opinion and Nigeria’s own experts (for whatever reason) had not done the work required? Should the Tribunal have taken the initiative to encourage exploration of new bounds of contract law and the law of damages that may today be required where major long term contracts are involved?

— R. Knowles CBE. FRN v. Process & Industrial Developments Limited [2023] EWHC 2638 (Comm)

Was this dictum helpful?

ISSUE OF JURISDICTION CAN ONLY BE RAISED AT THE ARBITRATION PANEL

The law therefore is that although in the regular Courts, the issue of jurisdiction can be raised at all stages of the proceedings of a case; from the trial to the final appellate, where a statute prescribed the stage at which the issue is to be raised in the course of the proceedings of a case, the issue cannot be validly and properly raised at any other stage other than the one stipulated in the statute. The general principle applies only where there was no statutory provision as to the particular or specific stage of the proceedings of a case at which the issue of jurisdiction is to be raised by a party.

– Garba, JCA. Dunlop v. Gaslink (2018)

Was this dictum helpful?

No more related dictum to show.