Parties are bound by the terms of the agreement they have voluntarily entered into. The only function of the court is to interprete the agreement in enforceable terms without more.
[Kurubo v. Zach-Motison (Nig.) Ltd (1992) 5 NWLR (Pt. 239) 102; National Salt Co. (Nig.) Ltd v. Innis -Palnier (1992) 1 NWLR (Pt. 218) 422; Union Batik of Nigeria Ltd. v. Ozigi (1994) 3 NWLR (Pt. 333) 385; Shettiniari v. Nwokoye (1991) 9 NWLR (Pt. 213) 60]. – L.A. Ayanlere v. Federal Mortgage Bank of Nig. Ltd. (1998) – CA/K/186/96

Was this dictum helpful?

SHARE ON

TERMINATION OF CONTRACT OF SERVICE BRINGS TO AN END MASTER-SERVANT RELATIONSHIP

Chukuma v. Shell Petroleum Development Company (1993) 4 NWLR (Pt. 289) 512 at 560 where Karibi-Whyte JSC said: “In the ordinary case and following the common law principle,termination of a contract of service even if unlawful brings to an end the relationship of master and servant, employer and employee. This rule is based on the...

Membership Required

You must be a member to access this content.

View Membership Levels

Already a member? Log in here

A DIVISIBLE CONTRACT

A divisible contract is separable into parts, so that separate parts of the agreed consideration may be assigned to severable parts of the performance. Such divisible agreements admit of pro rata payments for each portion that was performed, and is independent of performance of other parts of the contract. — J.A. Fabiyi, JSC. BFI v....

Membership Required

You must be a member to access this content.

View Membership Levels

Already a member? Log in here

AWARD OF DAMAGES FOLLOWS BREACH OF CONTRACT

An award of damages usually follows a breach of contract so as to compensate the injured party for loss following naturally and within the contemplation of the parties. Damages is attached to a breach following an enforceable contract. Where there was no such contract an award of damages by any Court is not only a...

Membership Required

You must be a member to access this content.

View Membership Levels

Already a member? Log in here

WHEN INTERPRETING A CONTRACTUAL DOCUMENT THE WHOLE DOCUMENT SHOULD BE TAKEN CONSIDERATION OF

I am in full support of the submission of appellant’s counsel that it was a misdirection for the lower court in consideration of whether the land, the subject matter in controversy, was bare land or included the structures thereon to have relied on only clauses 3 and 6 in the entire lease agreement to arrive...

Membership Required

You must be a member to access this content.

View Membership Levels

Already a member? Log in here

WRONGFULLY TERMINATED CONTRACT

Where an employee’s appointment is wrongfully terminated, his remedy lies in an action for damages, because the court cannot force an employer to keep an employee in his services if the employee’s services are no longer required. The normal measure of damages the employee would be entitled to, is what he would have earned over...